R5.2bn Potsdam upgrade on track for completion in 2027 – City of Cape Town
Twenty months into the large-scale upgrade of the Potsdam wastewater treatment works (WWTW), the City of Cape Town (CoCT) says the R5.2-billion project is on track to be completed in 2027.
The upgrade is being executed through two construction contracts – one for civil infrastructure and another for providing the mechanical and electrical infrastructure.
It is one of the city’s largest infrastructure projects, designed to more than double the plant's capacity from 47-million litres a day, to 100-million litres a day.
To date, the civil construction of the ultrafiltration plant has been completed.
This plant will allow for advanced treatment processes, such as micro-screening, ultrafiltration membrane technology and UV disinfection.
Also included is a treated effluent reuse pump station, increasing water availability to the city.
Construction of the process control facility is also under way. This will be the operational node for the plant, and will consist of a new control room, with a system to monitor the plant’s operations in real time.
This area will also be the administration block where the operations management team will be based.
The civils portion of the membrane bioreactor facility, inlet works and raw sewage pump station is also under construction.
This is the largest part of the project, and will increase the treatment capacity of the Potsdam WWTW to 100-million litres a day.
Civil construction of the dewatering plant has been completed and has been handed over to the mechanical and electrical contractor for equipment installation.
This includes eight new primary sludge belt presses and eight new secondary sludge belt presses for dewatering of the respective sludges.
This facility will assist the plant in maintaining a consistent sludge age – or, good bacteria levels – ensuring improved treated effluent quality.
The dewatering and ultrafiltration installations are likely to be commissioned in the middle of next year.
This is anticipated to have a positive impact on existing operations, as it may realise improved treated effluent quality at the WWTW at an earlier stage.
CoCT says it aims for the completed treatment works to start operational trials in 2026.
“The city is steadily working towards restoring the environmental health of the Diep river and the Milnerton lagoon through a combination of efforts,” notes CoCT Water and Sanitation MMC Zahid Badroodien.
“The major infrastructure upgrades within the area at Potsdam WWTW are instrumental in achieving this, and we are looking forward to seeing more progress on site over the coming months.”
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation