The reconditioning of scraper idlers on a submerged scraper conveyor (SCC) has increased the average mean time between failures (MTBF) from between three months and six months to between 12 months and 18 months.
SKF asserts that this increase in MTBF was achieved with the use of the company’s sealed bearings, combined with upgraded internal modifications and locally manufactured custom seals.
The submerged scraper idlers convey water-quenched, hot coarse ash to the front of the SSC which then collects and dewaters the boiler bottom ash before discharging it at a controlled rate onto downstream plant. The SSC’s water-filled top trough, which works in conjunction with the dipper plates, provides boiler sealing by preventing air ingress into the boiler via the SSC.
The cost of frequent plant downtime to replace the failed scraper idlers was further exacerbated by the regular purchase of new units. SKF proposed the supply of sealed spherical roller bearings, a quality reconditioning procedure on the scraper idlers and an overall redesign of the internal sealing arrangement. SKF senior application engineer Cody Petersen explains that the highly contaminated operating conditions called for the use of sealed bearings, which help eliminate contaminant ingress, and increase overall bearing life expectancy, equipment availability and application running time.
The SKF team carried out a redesign of the entire internal geometry, shaft, hub and guide wheel. “We also manufactured custom seal cartridges to house custom seals manufactured by SKF locally and we partnered with an accredited SKF supplier to recondition the housings,” added Petersen.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation