Rook 1 uranium project, Canada – update

Image of the periodic table symbol for uranium

29th November 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Rook 1 uranium project.

Location
Saskatchewan, Canada.

Project Owner/s
Uranium developer NexGen Energy.

Project Description
Rook 1 is the biggest development-stage uranium project in Canada.

The project hosts the Arrow deposit, which, in turn, hosts measured and indicated mineral resources of 256.7-million pounds of uranium contained in 3.75-million tonnes grading 3.1%.

The project has a mine life of 10.7 years, with average production estimated at up to 30-million pounds a year.

Average life-of-mine production is estimated at 21.7-million pounds a year of uranium.

Access to the underground Arrow deposit will be through two shafts, an 8-m-diameter production shaft (intake air) and a 5.5-m-diameter exhaust shaft (second egress). Access to the workings will be from the production shaft.

Conventional longhole mining will be used for production. The mining method will use mechanised equipment and conventional processes widely employed in the global mining industry.

The estimated mill capacity is targeted stated at 1 300 t/d of ore.

The key infrastructure contemplated includes:

  • underground infrastructure, including materials handling systems, maintenance facilities, a fuel bay, an explosives magazine, ventilation, a paste backfill and a paste tailings distribution system, electrical and communications facilities, underground water supply and dewatering facilities.
  • an underground tailings management facility.
  • surface support infrastructure for the mine, including headframe and hoist facilities, a surface explosives magazine and ventilation fans.
  • surface support infrastructure for the mill, including a process plant, a solvent-extraction plant, an effluent treatment plant and an acid plant.
  • site support infrastructure, including an accommodation camp, liquefied natural gas (LNG) facilities, an LNG power plant, mine and mill dry facilities, analytical and metallurgical laboratory and maintenance, as well as warehouse and security buildings.
  • a surface ore-storage stockpile facility, as well as waste-rock storage facilities for potentially acid-generating, nonpotentially acid-generating and special waste materials.
  • water management facilities, consisting of two site water runoff ponds, six contact water process ponds, a potential acid-generating stockpile runoff collection pond, and conveyance and diversion structures.
  • domestic and/or industrial waste management areas.
  • an airstrip.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of C$6.32-billion and an internal rate of return of 45.2%, with a payback of one year, based on a uranium price of $95/lb.

Capital Expenditure
C$2.2-billion.

Planned Start/End Date
Not stated.

Latest Developments
NexGen Energy has announced a significant milestone in the federal environmental assessment (EA) for its Rook I project.

The Canadian Nuclear Safety Commission (CNSC) has provided NexGen formal confirmation that the company has successfully addressed all information requests received as part of the federal technical review.

With completion of the CNSC technical review, the next and final steps in the federal approval process include scheduling a commission hearing date for the project, subject to which the CNSC will render an approval decision on the project.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
NexGen Energy, tel +1 306 954 2275.

Edited by Creamer Media Reporter

Comments

 

Showroom

Weir
Weir

Weir is a global leader in mining technology. We recognise that our planet’s future depends on the transition to renewable energy, and that...

VISIT SHOWROOM 
Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.34 0.49s - 200pq - 2rq
Subscribe Now