https://newsletter.en.creamermedia.com
Africa|Energy|Financial|Generators|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|Resources|Solar|System|Solutions|Infrastructure
Africa|Energy|Financial|Generators|Power|PROJECT|Projects|Renewable Energy|Renewable-Energy|Resources|Solar|System|Solutions|Infrastructure
africa|energy|financial|generators|power|project|projects|renewable-energy|renewable-energy-company|resources|solar|system|solutions|infrastructure

SAWEA expresses grave concern over grid-access rules as no wind project prevails under expanded bidding round

Grid access emerges as hurdle to wind projects in South Africa

Grid access emerges as major hurdle to wind projects in South Africa

8th December 2022

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

The South African Wind Energy Association (SAWEA) has expressed dismay that none of the 23 wind-project bids submitted as part of government’s latest and expanded renewables procurement round were selected as preferred bidders and expressed concern about the current system for allocating grid access.

Mineral Resources and Energy Minister Gwede Mantashe announced on December 8 that only six solar projects, with a combined capacity of 1 000 MW, had been appointed as preferred bidders following the sixth bid window (BW6) of the Renewable Energy Independent Power Producer Procurement Progamme.

This despite the round having been expanded from 2 600 MW to 4 200 MW as part of a series of initiatives, announced by President Cyril Ramaphosa in July, to tackle intensifying loadshedding, which was being implemented at Stage 6 at the time of the announcement.

A total of 56 wind and solar bids were received by the bid submission deadline and IPP Office head Bernard Magoro attributed the low conversion rate to the fact that Eskom no longer had grid capacity available, mostly in the Cape provinces, to absorb the generators bid under BW6.

Eskom transmission MD Segomoco Scheepers said the non-discriminatory access rules of the Grid Code meant that Eskom could not reserve grid access for BW6 projects where other IPPs had made financial commitments to gain access to the capacity.

However, SAWEA argued that Eskom needed to be more responsible in managing grid access with a balanced view between publicly and privately procured electricity.

“A clearly defined queueing system needs to be urgently implemented,” CEO Niveshen Govender said in a statement.

Under BW6, bidders were required to secure cost estimate letters from Eskom for grid access but were unable to pay for Budget Quotes until they were named as preferred bidders. In the interim, developers of projects with private offtakers secured Budget Quotes for the very same grid access on which the BW6 bids were reliant.

SAWEA noted that wind developers had been guided by Eskom’s recently published Generation Connection Capacity Assessment, which indicated that there was grid availability for public procurement.

“We agree with Minister Mantashe that investment into the grid infrastructure must be prioritised and accelerated to allow for more new generation capacity, however, grid-access processes are providing little confidence in articulating how grid capacity is being allocated and we view the announcement today as a missed opportunity given our dire need for electricity in South Africa,” Govender said, while calling for a balanced view between publicly and privately procured electricity.

“We strongly urge immediate intervention by key role-players to unpack the challenges with the wind sector and find viable solutions to unlock the hurdles facing the progression toward a secure energy system,” he added.

Had all 23 wind projects been built, they would have contributed 10 TWh yearly, and could have contributed significantly to combating loadshedding, which was being implemented at Stage 6 when the decision to exclude the projects was announced.

Edited by Creamer Media Reporter

Comments

Projects

Showroom

Weir
Weir

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 
John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 22 November 2024
Magazine round up | 22 November 2024
22nd November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.153 0.251s - 198pq - 4rq
Subscribe Now