Artemis in final stages of Blackwater commissioning

The tailings storage facility at Blackwater

The tailings storage facility at Blackwater

The tailings storage facility at Blackwater

25th November 2024

By: Creamer Media Reporter

     

Font size: - +

The Blackwater gold mine, in central British Columbia, is in the final stages of construction and commissioning, with the first gold pour scheduled before the end of the year.

In a project update last week, Artemis reported that mining operations in the openpit had started.

First ore has been fed to the processing facility’s crushing circuits. The commissioning team is set to hand over the crushing circuit to the operations team in the next few weeks.

The tailings storage facility (TSF) construction activity is also complete and the TSF is ready for production.

Phase 1 of Blackwater entails a six-million-tonne-a-year initial throughput. In Phase 2, this will increase to nine-million tonnes a year in the fifth year, ramping up to 12-million tonnes a year in the sixth year. Phase 3 will boost throughput to up to 20-million tonnes a year. 

Edited by Creamer Media Reporter

Comments

 
 

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
M and J Mining
M and J Mining

M and J Mining are leading suppliers of physical support systems as used by the underground mining industry. Our selection of products are not...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.26 0.355s - 192pq - 2rq
Subscribe Now