Boiler relocation project near completion

MAINTENANCE 
The installation of a pumped condensate system and a refurbished pressure control system at the Majola Tea project were completed

MAINTENANCE The installation of a pumped condensate system and a refurbished pressure control system at the Majola Tea project were completed

25th January 2019

By: Thabi Shomolekae

Creamer Media Senior Writer

     

Font size: - +

Boiler maintenance and installations provider Boiler & Industrial Plant hopes to complete the boiler relocation project it has been working on for manufacturer United National Breweries (UNB), commonly known as Ijuba breweries, by the end of this month.

The project, valued at R2-million, comprises relocating boiler and environmental solutions company John Thompson’s 6.3 t coal boiler from the premises of UNB Khangela Brewery, in Durban, and installing it at the UNB Isithebe Malt Plant, in Manoeni, on the KwaZulu-Natal North Coast, as well as the relocating of John Thompson’s 8 t coal boiler from UNB Isithebe and installing it at UNB Tlokwe Brewery, in Potchefstroom. The project also involved the relocation of forty-four 22 000 ℓ stainless steel tanks from UNB Khangela to UNB Isithebe.

“UNB was going through a major reshuffle, which led to the Durban-based plant having been shut down. However, this has resulted in an exciting project that Boiler & Industrial Plant successfully tendered,” says Boiler & Industrial Plant director Bryan Swanepoel.

The tender was awarded to Boiler & Industrial Plant in November 2018 and Swanepoel relays that the company carried out the work in a very short period, having begun with removing the equipment from the Durban site by the end of November.

Swanepoel adds that, to date, Boiler & Industrial Plant has completed the installation and associated piping installations, as well as the legally required testing and certification of the relocated boilers.

Boiler & Industrial Plant has also completed the R7-million tea plantation project at Magwa Tea and Majola Tea, in the Eastern Cape. The two plantations have not been in commercial operation for many years, owing to unknown reasons.

Bringing the plantations back into commercial operation will create employment for the local communities, Swanepoel comments.

Work at Magwa Tea started in September 2018, which entailed successfully putting steam through the plant in early November, thus allowing for the first tea crop to be picked. Work at Majola Tea started in October and the plant was commissioned in December.

The Magwa Tea project comprised the statutory inspection of two of the 8 t John Thompson boilers and retubing one boiler, complete refurbishment of two stokers, and the installation of new lagging and stainless steel cladding for the boilers. Swanepoel says clients can now expect fuel savings of between 6% and 10%, as well as electrical savings, owing to the VSD and PLC control system.

The Majola Tea project comprised the statutory inspection of the 4 t John Thompson boiler, complete refurbishment of the stoker and the installation of new lagging and stainless steel cladding for the boiler.

Edited by Zandile Mavuso
Creamer Media Senior Deputy Editor: Features

Comments

 

Showroom

Flameblock
Flameblock

FlameBlock is a proudly South African company that engineers, manufactures and supplies fire intumescent and retardant products to the fire...

VISIT SHOWROOM 
Multotec
Multotec

Multotec, recognised industry leaders in metallurgy and process engineering help mining houses across the world process minerals more efficiently,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.343 0.448s - 310pq - 2rq
Subscribe Now