Eskom ordered to pay French company R1bn-plus over Koeberg dispute – Business Day
State-owned utility Eskom has been ordered by a high court to pay more than R1-billion to French nuclear energy company Framatome, after contract and project management problems delayed a steam generator swap at the entity’s Koeberg nuclear power plant, newspaper Business Day reports.
In an article on July 21, reporter Kabelo Khumalo reports that the adjudication process, which was handled by advocate Peter Ramsden, resulted in the court ordering Eskom to pay Framatome €35.2-million (R727-million) and a further R256.6-million, in line with Ramsden’s earlier findings.
This excludes value-added tax, interest and Framatome’s French-based attorney’s fees.
The dispute arose in 2022 when Eskom took Koeberg Unit 2 offline, for what it said would be a five-month outage to refuel and replace its three steam generators. However, Eskom months later informed Framatome that it would not be continuing with the work, leaving the latter to claim compensation for breach of contract, Khumalo reports.
The article indicates that Eskom was of the view that the utility and the contractor were both responsible for the delays, arguing that both parties had contributed to the deficiencies.
Framatome, however, blamed Eskom, citing the utility’s role in contributing to delays as including that the facilities required to house the old steam generators, once removed, were not ready for use.
Engineering News in March 2022 reported that Eskom had announced the deferral of a project to replace three steam generators at Koeberg Unit 2 to August 2023 following a review, conducted with Framatome, which indicated that the replacements were unlikely to be completed within the six-month timeframe allocated for the project.
Then COO Jan Oberholzer had indicated that certain facilities, including the completion of the building that would house the radioactive steam generators being removed, were deemed to be not fully in place to ensure that the replacement could be completed to expected quality and schedule parameters, Engineering News reported.
The parties then engaged an adjudicator over the dispute, Khumalo reports, informing that Eskom did not participate in the adjudication, and then challenged the adjudicator’s findings in court.
The court described Eskom’s legal submissions as “contrived and unconvincing” and refused to set aside Ramsden’s award, the article points out.
Engineering News has also reported that Eskom this month announced a delay to the return of Koeberg Unit 1 from another extended maintenance outage; however, the entity insisted that the risk of loadshedding this winter had not increased as a result.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation