https://newsletter.en.creamermedia.com
Contractor|Design|Energy|Engineering|engineering news|Eskom|Gas|Generators|Infrastructure|Installation|Motors|Power|Renewable Energy|Renewable-Energy|System|Maintenance|Infrastructure|Operations
Contractor|Design|Energy|Engineering|engineering news|Eskom|Gas|Generators|Infrastructure|Installation|Motors|Power|Renewable Energy|Renewable-Energy|System|Maintenance|Infrastructure|Operations
contractor|design|energy|engineering|engineering-news|eskom|gas|generators|infrastructure|installation|motors|power|renewable-energy|renewable-energy-company|system|maintenance|infrastructure|operations

Eskom to add synchronous condensers to network, including repurposed Camden and Grootvlei generators

Map showing the proposed locations for installing synchronous condensers

Map showing the proposed locations for installing synchronous condensers

Photo by Eskom

20th November 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Eskom is preparing to introduce 11 synchronous condensers – seven new and four repurposed – across its transmission system to support grid stability as the penetration of variable renewable-energy generators rises.

The need for the synchronous condensers – to provide dynamic voltage support, inertia and short-circuit current required for the integration of inverter-based technologies – was identified in a recent power system modelling study conducted by the State-owned company.

The study indicated that the first seven synchronous condensers would be required by 2027.

Eskom Transmission MD Segomoco Scheppers reports that various sizes of synchronous condensers will be introduced at different nodes across the transmission grid, including two apiece at the Camden and Grootvlei power stations, where generators will be repurposed to perform synchronous-condenser functions when the stations are decommissioned.

Eskom tells Engineering News that the seven new synchronous condensers are planned for installation at, or near to, the existing substations of Aggeneis, Gromis, Gamma, Koruson, Grassridge, and two at Ferrum.

The study also indicated the need for synchronous-condenser functionality in the vicinity of the Avon open-cycle gas turbine plant, in KwaZulu-Natal.

“Following power system analysis and simulation studies performed on the transmission network, based on our assumptions on renewable energy integration and the projected decommissioning plans for some of the baseload synchronous power stations (as indicated in the IRP 2019), the locations and sizes of the synchronous condensers were determined,” Eskom tells Engineering News.

“The location of the synchronous condensers also confirms that they are required to support the network in areas with high renewable-energy penetrations.”

No final capital investment figure has been provided, but Eskom expects the cost  associated with repurposing generators at Camden and Grootvlei to be lower than the purchase of new machines, which are synchronous motors where the shaft is not connected to anything and spins freely.

Conversion costs are estimated at between $20 000/MVAr and $50 000/MVAr, while the cost of new synchronous condensers is expected to be at least double that level.

“We will follow our Eskom procurement process to appoint an EPC contractor to design, construct and commission the infrastructure and hand-over to Eskom Transmission for operations and maintenance,” Eskom confirms.

Edited by Creamer Media Reporter

Comments

Showroom

John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 
Willard
Willard

Rooted in the hearts of South Africans, combining technology and a quest for perfection to bring you a battery of peerless standing. Willard...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.08 0.185s - 216pq - 4rq
Subscribe Now