https://newsletter.en.creamermedia.com
Africa|boilers|Castings|Civils|Coal|Coal-fired Power Station|Components|Concrete|Construction|Consulting|Contractor|Conveyors|Cranes|Electrical|Energy|Engineering|Eskom|Export|Fabrication|Flow|Gas|generation|Generator|HPE|Industrial|Infrastructure|Installation|Materials Handling|Nuclear|Pipelines|Pipes|Power|PROJECT|Project Management|Projects|Pumps|Roads|Safety|SECURITY|Services|Siemens|Slurry|Steel|Storage|Switchgear|System|Systems|Technology|Testing|Transformers|transport|Valves|Water|WEG|Equipment|Flow|Products|Environmental|Infrastructure|Bearing|Bearings|Cables
Africa|boilers|Castings|Civils|Coal|Coal-fired Power Station|Components|Concrete|Construction|Consulting|Contractor|Conveyors|Cranes|Electrical|Energy|Engineering|Eskom|Export|Fabrication|Flow|Gas|generation|Generator|HPE|Industrial|Infrastructure|Installation|Materials Handling|Nuclear|Pipelines|Pipes|Power|PROJECT|Project Management|Projects|Pumps|Roads|Safety|SECURITY|Services|Siemens|Slurry|Steel|Storage|Switchgear|System|Systems|Technology|Testing|Transformers|transport|Valves|Water|WEG|Equipment|Flow|Products|Environmental|Infrastructure|Bearing|Bearings|Cables
africa|boilers|castings|civils|coal|coalfired-power-station|components|concrete|construction|consulting-company|contractor|conveyors|cranes|electrical|energy|engineering|eskom|export|fabrication|flow-company|gas|generation|generator|hpe|industrial|infrastructure|installation|materials-handling|nuclear|pipelines|pipes|power|project|project-management|projects|pumps|roads|safety|security|services|siemens|slurry|steel|storage|switchgear|system|systems|technology|testing|transformers|transport|valves|water|WEG|equipment|flow-industry-term|products|environmental|infrastructure|bearing|bearings|cables

Kusile power plant project, South Africa – update

Image of the Kusile power station

5th July 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Kusile power plant project.

Location
Near the Kendal power station, in the Nkangala district of Mpumalanga, in South Africa.

Project Owner/s
State-owned power utility Eskom.

Project Description
The Kusile power station project will comprise six units, each rated at an 800 MW installed capacity for a total capacity of 4 800 MW. Once completed, Kusile will be the fourth-largest coal-fired power station in the world.

The Kusile project will include a power station precinct, power station buildings, administrative buildings (control buildings and buildings for medical and security purposes), roads and a high-voltage yard.

The associated infrastructure will include a coal stockyard, coal and ash conveyors, temporary and permanent water-supply pipelines, temporary electricity supply during construction, water and wastewater treatment facilities, ash disposal systems, a railway line, limestone offloading facilities, access roads (including haul roads) and dams for water storage, as well as a railway siding and railway line to transport the limestone supply (sorbent).

The power station will be the first in South Africa to install wet flue-gas desulphurisation (FGD) – a state-of-the-art technology used to remove oxides of sulphur, such as sulphur dioxide, from exhaust flue gases in power plants that burn coal or oil.

This technology abates atmospheric emissions, in line with current international practice, to ensure compliance with air-quality standards, especially since the power station is located in a priority air-shed area.

The wet FGD plant is a totally integrated chemical plant using limestone as feedstock and producing gypsum as a by-product.

Each supercritical tower boiler will be about 115 m high. The air-cooled condensers will be built on and supported by twenty 60-m-high concrete columns.

Potential Job Creation
A comprehensive exit and outreach strategy, which aims to gradually upskill and release local labour to the job market, has been formalised in partnership with key stakeholders. This allows for project stability amid the gradual demobilisation of workers once milestones are achieved, and mitigating the risk of local community disruptions.

Capital Expenditure
R233.4-billion.

Planned Start/End Date
Kusile Unit 1 achieved commercial operation on August 30, 2017.

Kusile Unit 2 achieved first synchronisation on March 24, 2018, and achieved full load in January 2019. Commercial operation was achieved on October 29, 2020.

Kusile Unit 3 achieved first synchronisation on April 14, 2019, eight months ahead of schedule. Commercial operation was achieved in March 2021.

Kusile Unit 4 was connected to the national grid for the first time on December 23, 2021, and was formally handed over to the Eskom generation division on May 31, 2022, following five months of testing and optimisation.

However, units 1 to 3, which have a combined capacity of 2 100 MW, became inoperable on October 22, 2022, after the Unit 1 flue duct collapsed because of a build-up of slurry. The collapse also compromised the unit 2 and 3 flue ducts, which share a common chimney with the Unit 1 flue.

Kusile Unit 5 was synchronised to the grid on December 31, 2023, and was formally handed over to the Eskom generation division on June 30, 2024, following six months of testing and optimisation.

Latest Developments
Following six months of testing and optimisation, Eskom transferred Unit 5 to its generation division on June 30. The handover of the generation unit marks a significant milestone in the company's ongoing efforts to stabilise South Africa’s power system.

The unit will now start contributing power, increasing Kusile’s total output to 4 000 MW.

Over the past six months, Kusile Unit 5 has undergone a series of tests while intermittently supplying electricity. Since its synchronisation in December 2023, the unit has met performance expectations, supported the grid and helped to reduce loadshedding.

Construction of Unit 6 is progressing as planned, and is expected to be synchronised to the grid in November 2024.

Key Contracts, Suppliers and Consultants
Eskom, in partnership with Black & Veatch International (project management and engineering services); Ninham Shand Consulting Services (environmental-impact assessment, geotechnical investigation and traffic impact); AirShed Planning Professionals (air-quality impact); Jongens Keet Associates (noise impact); Strategic Environmental Focus, or SEF (visual impacts); Makecha Development Association (impacts on terrestrial fauna and flora); Golder Associates, through Ecosun (aquatic-ecosystem impact); Groundwater Consulting Services (groundwater impact); Ilitha Riscom (risk assessment); Northern Flagship Institution (archaeological impact); University of the Free State (impacts on agricultural potential); Urban-Econ (socioeconomic impacts); Seaton Thomson & Associates (planning implications); Mark Wood Environmental Consultants (process review); Mitsubishi Hitachi Power Systems Africa, or MHPSA, a subsidiary of Hitachi Power Europe, or HPE (boiler contract); Actom, formerly Alstom S&E Africa (main turbine area); ABB SA (C&I, including supply of medium-voltage switchgear and associated equipment); Mikropul, subcontracted by Alstom (axial-flow fans and auxiliary equipment for the turbine halls' ventilation); GE (EPC of six turbine islands, air-cooled condensers and WFGD); Alstom (WFGD); Murray & Roberts, or M&R (boiler construction contract); Roshcon, a subsidiary of Eskom (enabling civils, terracing construction and site services); Concrete Finishing Equipment (dust filters, and silo and environmental safety); Kusile Civil Works, or KCW, Joint Venture (JV), comprising Stefanutti Stocks, Basil Read, Group Five and WBHO Construction (main civil works); Siemens (generator transformers and electrical and auxiliary power); EsorFranki Geotechnical, formerly Franki Africa, and Stefanutti Stocks Geotechnical JV, under a subcontract to KCW JV (piling works for the turbine, boiler and air-cooled condensers); Concor Karrena JV (construction of chimney shells/structures); Tubular (engineering, supply and installation of FGD system); DSE Structural Engineers & Contractors, subcontracted by Genrec Engineering (fabrication of steel columns for boilers 1 to 3); Steel Services Direct, or SSD (steel, pipes and wax plants); GB Bearings (supplier of HSR horizontal bearing assemblies and profile bore bearings); Sulzer Pumps South Africa, subcontracted by Actom (supply of booster and boiler feed pumps); Steloy Castings, subcontracted by Sulzer Pumps South Africa (supply of chrome steel components for the pumps); Clyde Bergemann Power Group, subcontracted by MHPSA (supplier of sootblowers for boilers); Clyde Bergemann Africa (fly ash handling system); PD Naidoo & Associates, or PDNA, Industrial Projects (main water and wastewater treatment contractor); GE Water Engineered Systems, subcontracted by PDNA Industrial Projects (advanced water and wastewater treatment equipment); Bateman Africa (coal stockyard and terrace materials handling systems); Lesedi Nuclear Services (procurement and supply of the balance of plant equipment); Grinaker-LTA Metals & Minerals (supply and erection of piping, steelwork and free-issue chemicals); US Export-Import Bank, or Ex-Im Bank (loan finance); TBD (railroad construction and combustion water terrace construction phases 1 and 2); Zest WEG Group (auxiliary transformers); Aberdare Cables, a Powertech company within the JSE-listed Altron Group (cables); Konecranes (heavy duty cranes); Energy Engineered Products (supply of valves); and Turnmill Proquip Engineering (material for boiler ducting).

Contact Details for Project Information
Eskom media desk, email mediadesk@eskom.co.za.

Edited by Creamer Media Reporter

Comments

 

Showroom

Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 
WearCheck
WearCheck

Leading condition monitoring specialists, WearCheck, help boost machinery lifespan and reduce catastrophic component failure through the scientific...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.193 0.352s - 202pq - 2rq
Subscribe Now