Lonmin Furnace One shutdown not expected to affect production

8th December 2014

By: Chantelle Kotze

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Platinum-mining company Lonmin expects the repair of its Number One furnace to take about three months, following its shutdown without incident after a leak of molten furnace matte was detected.

The company announced on Monday that an assessment of the furnace revealed that mechanical structure and refractories below the tap hole and the copper tap block needed to be replaced.

While the life of Number One furnace had been extended through careful operation, it was impossible to operate the smelter on a consistent basis during the five-month platinum strike.

Lonmin intended to mitigate operational risk while undertaking repairs to the furnace by bringing forward its planned hearth rebuild, which was originally scheduled and budgeted for October 2015.

The repair was not expected to affect the miner’s refined production for the 2015 financial year as its back-up facilities for such events had been put into operation.

While the furnace was out of commission the Number Two furnace would continue to operate and Lonmin had restarted its three smaller Pyromet furnaces.

The stopping of the Number One furnace had the potential to back-end load sales into the second half of the 2015 financial year and there would be a build-up of concentrate stocks, which was expected to unwind by the end of the year.

While Lonmin was assessing commercial ways to mitigate this, it was maintaining its overall sales and unit cost guidance for the 2015 financial year.

Although the company expected its net borrowings to increase at the end of March 2015 as a direct result of the lower sales volume in the first half of the year, the platinum producer was expected to remain well within its borrowing facilities. The capital spend for the repairs would be absorbed into the guided capital spend for the year.

Edited by Tracy Klückow
Creamer Media Contributing Editor

Comments

Research Reports

Latest Multimedia

Latest News

Sibanye-Stillwater CEO Richard Stewart.
Sibanye-Stillwater CEO transition complete, ex-PIC head leading business development
1st October 2025 By: Martin Creamer

Showroom

AQS Liquid Transfer
AQS Liquid Transfer

AxFlow AQS Liquid Transfer (Pty) Ltd is an Importer and Distributor of Pumps in Southern Africa

VISIT SHOWROOM 
Schauenburg SmartMine IoT
Schauenburg SmartMine IoT

SmartMine IoT has been developed with the mining industry in mind, to provides our customers with powerful business intelligence and data modelling...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Image of Sun City Hotel
New era for Sun City after transformation
29th September 2025 By: Natasha Odendaal
Photo of Terence Creamer
Govt moves to end load reduction
26th September 2025 By: Creamer Media Reporter

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.065 1.81s - 182pq - 2rq
Subscribe Now