Nakambala sugar mill expansion project completed
NAKAMBALA SUGAR MILL Illovo Sugar appointed Bosch Projects as engineering, procurement and construction management consultants for the mill’s expansion
STEVEN ROSETTENSTEIN Undertaking the expansion project has provided Bosch Projects with the experience and capabilities to handle future refinery projects of this nature
During the third quarter of 2017, project management and equipment design company Bosch Projects completed the implementation of the Nakambala Product Alignment and Refinery project in Mazabuka, Zambia.
Bosch Projects sugar sector director Steven Rosettenstein, who was the project manager for the Nakambala project, says the project was commissioned in April/May last year. Africa’s largest sugar producer, Illovo Sugar, appointed Bosch Projects the engineering, procurement and construction management consultant for its subsidiary, Zambia Sugar, which owns and operates Nakambala.
The contract involved the expansion of the raw house production capacity and the installation of a new sugar refinery, sugar conditioning plant and packing plant. Bosch Projects was responsible for the design and construction of a modern, high-specification refinery that more than doubled the factory’s yearly refined sugar production to 90 000 t.
A contributing factor to Illovo Sugar’s choosing Bosch Projects was that Bosch Projects had conducted the prefeasibility and feasibility study for this project, coupled with its extensive record in sugar projects of this nature.
The project consolidated Zambia Sugar’s position as Africa’s biggest sugar cane producer and underlined Illovo’s broader group strategy to conduct growth in its domestic and regional markets and downstream opportunities to diversify its product mix.
Meanwhile, implementing the project created many temporary jobs for local labour during construction, as well as permanent jobs for those operating the new refinery. Zambia and the Southern Africa region will continue to benefit from the project, owing to the supply of refined sugar into the region.
This project was the first greenfield refinery project that Bosch Projects has implemented. Rosettenstein enthuses that this new venture has provided the company with experience and capabilities for similar refinery projects in the future.
It has also been one of the largest projects that the company has undertaken to date. Rosettenstein notes that the timeframe for project completion – which was very tight from the start – rather than the magnitude thereof, was the biggest challenge. However, regular scheduled reviews and the close management of contractors – which subsequently allowed for prompt corrective actions to be taken – ensured that project milestones were met.
Rosettenstein notes that the company leveraged its experience from previous similar projects to ensure that this project was set up correctly from the start. Resources used in previous projects were also used by the project team for this project. Experience gained from previous projects is also built into Bosch Project’s quality management system, which was used to deliver a “quality project” to Zambia Sugar, he adds.
Rosettenstein reiterates that the project was successfully executed, having achieved all the project objectives. The project received the Consulting Engineers South Africa (Cesa) Commendation Award for Best International Project at the annual Cesa Excellence Awards event that was held in August 2016 at Vodacom World, in Midrand, Johannesburg.
Equipment Provider
Bosch Projects also completed the design and supply of sugar processing equipment for this project in June 2015 and delivered this equipment to Nakambala from October to December 2015.
Several items of sugar processing equipment were supplied, each with specific performance parameters. Rosettenstein says this equipment is unique to the sugar industry, for example, the continuous vacuum pan, which has a patented design. Other equipment included clear juice heaters, a vacuum seed receiver, condensate flash vessels, condensers, water clarifier, a refinery evaporator, a 50-m-high refined sugar conditioning silo, and a lime and liquor wheel.
“All the equipment was designed in-house in Durban. This was beneficial because it allowed Bosch Projects to maintain control of the design and protect it from being replicated. It also allowed for flexibility to modify and improve the design, thus providing more marketable and competitive equipment,” he explains.
The equipment was transported by road from Durban to Zambia. Rosettenstein indicates that the average transit time was eight days, including abnormal loads. Illovo was responsible for the transport logistics, which he says was well managed through accurate paperwork and completed custom clearings.
Following the expansion, the equipment will continue to be used to increase the throughput and performance of the factory, Rosettenstein concludes.
Comments
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation