https://newsletter.en.creamermedia.com
Contractor|Cranes|Design|Efficiency|Engineering|generation|heavy lift|Innovation|Installation|Lifting|Marine|Modular|Power|PROJECT|Projects|Services|Storage|System|transport|Turbines|Water|Equipment|Solutions|Turbines|Bearing
Contractor|Cranes|Design|Efficiency|Engineering|generation|heavy lift|Innovation|Installation|Lifting|Marine|Modular|Power|PROJECT|Projects|Services|Storage|System|transport|Turbines|Water|Equipment|Solutions|Turbines|Bearing
contractor|cranes|design|efficiency|engineering|generation|heavy_lift|innovation|installation|lifting|marine|modular|power|project|projects|services|storage|system|transport|turbines-company|water|equipment|solutions|turbines-person|bearing

Next generation monopiles moved using time- and cost-effective new tech

A generic image of a wind turbine compoent

HEAVY INNOVATION Purpose-built lifting solutions simplify the safe handling of oversized monopiles for offshore wind farms

13th February 2026

     

Font size: - +

Wind turbine sizes are increasing at an unprecedented rate and for clear reason: the bigger the turbine, the more power it can generate and the fewer are needed for each wind farm, says engineering services and transportation company Mammoet.
 
Taller turbines require larger foundations to withstand heavier winds further out to sea, but as these foundations grow, they are becoming increasingly challenging to lift and transport.
 
As an expert in handling heavy items safely and efficiently, Mammoet has been ahead of the curve in developing ways to make the movement of even XXL monopiles faster and more cost-effective.
 
While it is theoretically possible to place monopiles into the sea using large crawler cranes, those required to meet the lifting capacity of the installation vessel would have been too big; requiring more space than was available at the port, and also reinforcement of its ground.
 
Mammoet, therefore, engineered an upgraded terminal crane that can lift large monopiles into the water for offshore feedering, and a specialist patented jacking-and-cradle system for their safe handling, using its self-propelled modular transporter (SPMT).
 
Mammoet’s equipment transformed the Port of Ronne, in Denmark, into a seamless assembly line, where monopiles were efficiently offloaded, stored, capped and then lifted into the water –  no civil work was needed to reinforce the quay.
 
The value of this solution was demonstrated during the marshalling scope for Windanker GmbH’s 315 MW Windanker offshore wind farm, which was being fed by Van Oord in the German waters of the Baltic Sea.

Better Support and Less Civil Work
The transport and installation of the 21 monopile foundations were overseen by global marine contractor Van Oord, with Mammoet supporting its onshore lifting and transport.
 
The monopiles arrived at the Port of Ronne from Spain, shipped in seven batches. The heaviest monopile weighed 2 150 t and measured about 87 m in length.
 
Fitted with Mammoet’s XXL monopile transport system, 90 axle lines of SPMT lifted the monopiles off their grillages and cradled them securely as they were driven off the vessel. 
 
They were then taken to a temporary storage location and placed onto sand bunds, ready to be called off for capping to make them watertight.
 
The added stroke of the XXL monopile transport system allowed the monopiles to be lifted higher so that the indents of the storage bunds could be deeper, improving their support while using fewer materials.
 
Next, at the capping location, a large LR1750 crawler crane installed plugs onto the top and bottom ends of each monopile.
 
Once both plugs were installed, the monopiles were driven to the quayside in front of the two MTC1600 cranes, which Mammoet developed specifically to lift XXL monopiles onto vessels and into waters.  
 
Once each monopile was safely in the sea, it was towed using tugs to Van Oord’s specialist heavy lift installation vessel, the Svanen, which was ready in the field to lift and install it into the seabed.
 
“We made a completely new crane design for this project, which is not typical but something we felt was necessary with the growth of monopile foundations,” explains Mammoet project manager Stefan de Vries.
 
“Once everything was agreed, we needed to ensure the new Mammoet Terminal Crane (MTC) cranes would be ready. We collaborated with Van Oord to make sure they would suit their needs.
 
“Initially, it was planned that the cranes would lift 2 800 t, but we suggested their maximum capacity match that of the Svanen, to ensure consistent limits across the project. So, we increased their combined lift capacity to 3 200 t.”
 
Foundations for Success 
With the ballast weight of the MTC crane positioned much further away from the pivot point of the boom, in comparison to a large crawler crane, the load-bearing pressure was far less. This helped to spread the load over a greater distance, avoiding the need for specialist foundations or temporary civil work.
 
Thanks to the efficiency of crane lifting, the Svanen could remain in the field and be constantly fed monopiles.
 
The result was an otherwise challenging marshalling project made simpler through a combination of knowledge, innovation and collaboration.
 
Through its considerable experience of monopile handling, Mammoet guides its customers to the safest and schedule-boosting methods to simplify complex marshalling projects.
 
It is also constantly innovating to ensure its transport and lifting solutions can support not just the wind farms of today, but those of tomorrow.

END

To watch Creamer Media's latest video reports, click here
 

Edited by Nadine James
Features Deputy Editor

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Latest Multimedia

Magazine round up | 13 February 2026
Magazine round up | 13 February 2026
Updated 47 minutes ago

Latest News

Aspen delivers encouraging interim performance
Aspen delivers encouraging interim performance
12th February 2026 By: Sabrina Jardim
Drought
Western Cape farmers lose cattle to drought
12th February 2026 By: Reuters

Showroom

ASTPM
ASTPM

Established in 1983, the ASTPM is an industry association and representative body of the welded carbon steel tube and pipe manufacturers of South...

VISIT SHOWROOM 
Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 06 February 2026
Magazine round up | 06 February 2026
6th February 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.219 0.331s - 196pq - 2rq
Subscribe Now