https://newsletter.en.creamermedia.com
Design|Hydraulics|Infrastructure|Installation|PROJECT|System|Systems|Valves|Water|Maintenance|Infrastructure|Operations
Design|Hydraulics|Infrastructure|Installation|PROJECT|System|Systems|Valves|Water|Maintenance|Infrastructure|Operations
design|hydraulics|infrastructure|installation|project|system|systems|valves|water|maintenance|infrastructure|operations

Rand Water prepares for final phase of maintenance

Water coming out of a tap

Photo by Bloomberg

24th July 2024

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

     

Font size: - +

Rand Water is set to embark on the final phase of its extensive five-week maintenance project across Gauteng, with the water utility warning that it may take up to two weeks to fully recover after the completion of the maintenance work.

The project, which started on June 22 and is expected to wrap up by the end of July, has been disruptive for many, with taps in several areas across Gauteng running dry for several days, as the systems worked to recover following the conclusion of a 50-hour maintenance project on the Zuikerbosch water treatment plant on July 17.

During the maintenance period, some reservoirs across the cities of Ekurhuleni, Johannesburg and Tshwane had experienced critically low levels, leading to low pressure or no water supply, particularly in high-lying areas.

Now Rand Water is preparing to start the last phase of its maintenance project on July 26, which will impact the normal pumping operations at the Mapleton and Palmiet Systems.

Rand Water, in a statement, said it is aware of the concerns that have been raised by its municipal customers regarding the slow recovery period of the systems during the maintenance work.

“Admittedly, there may be short-term inconveniences, such as low pressure to no water supply, but the long-term benefits are unparalleled. It is crucial to highlight that this maintenance work must be completed as scheduled to prepare for the high demand season,” the utility commented.

Rand Water further advised that the systems may take up to two weeks to fully recover after the completion of the maintenance work. However, different areas recover earlier than others owing to the design hydraulics of the systems.

“Rand Water has requested the affected municipalities to advise their customers on the extent and the impact of water supply in their respective areas, with the affected municipalities committing to continue providing alternative water supply to the residents.”

Maintenance work at the Mapleton System will start at 03h00 on July 26, with no pumping from this system for 77 hours until completion at 08h00 on July 29.

The project comprises the connection of the newly constructed engine room to the existing infrastructure, as well as final installation work to achieve commissioning of the new disinfection plants. In addition, the maintenance work will include the replacement of various valves.

Water users across the cities of Tshwane and Ekurhuleni, as well as the local municipalities of Thembisile Hani, Lesedi, Govan Mbeki and Victor Khanye will be affected.

Rand Water’s critical reservoirs that will be affected during the maintenance period include Brakpan, Vlakfontein, Selcourt, Wildebeesfontein, Stompiesfontein, Modder East and Bronberg.

Meanwhile, maintenance work to provide flexibility, along with the replacement of various valves, at the Zuikerbosch water treatment plant’s engine room 2 will impact water supply to the Palmiet pumping station.

Rand Water will undertake this work from 05h00 on July 29 to 21h00 on July 30, when pumping at the Palmiet pumping station will be at 76%, with 24% of the pumping capacity out of production.

Municipal customers that will be affected by the maintenance work impacting Palmiet System are the cities of Johannesburg, Tshwane and Ekurhuleni, as well as the Madibeng local municipality, with the critical reservoirs, namely Klipriviersberg, Germiston, Meyers Hill, Klipfontein, Brakfontein and Hartebeeshoek, impacted.

Edited by Creamer Media Reporter

Comments

 

Showroom

John Deere (Pty) Ltd
John Deere (Pty) Ltd

In 1958 John Deere Construction made its first introduction to the industry with their model 64 bulldozer.

VISIT SHOWROOM 
The Southern African Institute of Mining and Metallurgy
The Southern African Institute of Mining and Metallurgy

The SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.191 0.284s - 195pq - 2rq
Subscribe Now