Rand Water successfully completes first pipeline maintenance ahead of schedule

24th June 2024

By: Natasha Odendaal

Creamer Media Senior Deputy Editor

     

Font size: - +

Rand Water has successfully completed the proactive extensive maintenance of the F5 Pipeline in Mogale City local municipality, which started on June 22, nine hours ahead of schedule.

The project, which marked the start of the water utility’s extensive month-long maintenance plan across Gauteng, entailed connecting the F16 pipeline to the new F5 pipeline and to new meters.

During this period, the normal pumping of water was not affected as only one meter was impacted.

The next phase of the maintenance project started on June 24 at the Eikenhof, Zwartkopjes and Mapleton systems.

The Eikenhof pumping station has been reduced to 50% for eight hours before being increased to 67% for the following 64 hours, as Rand Water undertakes the maintenance work, which includes cleaning of the sedimentation tank at the Vereeniging water treatment plant (VWTP) and interconnecting the Waterval 1 and 2 reservoirs in the Eikenhof system.

At the Zwartkopjes system, Rand Water will replace a defective valve at the VWTP, which will result in the reduction of pumping to 50% for 27 hours.

The maintenance work at Trichardt will entail upgrading the transformer to increase power supply capacity; however, there will be no impact of water supply since there are generators at Trichardt.

Maintenance work at the Palmiet system will start on June 28.

Rand Water will provide updates throughout the maintenance period.

Edited by Creamer Media Reporter

Comments

 

Latest News

SAPVIA CEO Dr Rethabile Melamu
South Africa PV capacity increases 12% in 2024
20th December 2024 By: Schalk Burger

Showroom

Victaulic
Victaulic

Since 1919, Victaulic’s innovative solutions and design services continue to increase construction productivity and reduce risk, ensuring projects...

VISIT SHOWROOM 
ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.159 0.249s - 173pq - 2rq
Subscribe Now