https://newsletter.en.creamermedia.com
Construction|Design|Engineering|Financial|Infrastructure|Power|PROJECT|Projects|Roads|Solar|Water|Equipment|Environmental|Infrastructure
Construction|Design|Engineering|Financial|Infrastructure|Power|PROJECT|Projects|Roads|Solar|Water|Equipment|Environmental|Infrastructure
construction|design|engineering|financial|infrastructure|power|project|projects|roads|solar|water|equipment|environmental|infrastructure

Deep Yellow signs NamPower deal, progresses early works at Tumas uranium project

17th December 2025

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

ASX-listed Deep Yellow has taken another step towards development of its flagship Tumas uranium project in Namibia, announcing the execution of a transmission power supply agreement with State-owned utility NamPower, alongside continued progress on engineering, early works and project financing.

The uranium developer reported on Wednesday that its wholly owned subsidiary, Reptile Uranium Namibia, had signed the power supply agreement with NamPower, subject to conditions precedent including a final investment decision (FID) on the Tumas project.

Acting CEO Craig Barnes described the agreement as a milestone as the company continued to de-risk the greenfields project ahead of a potential construction decision.

“The execution of the power supply agreement with NamPower is another important step in advancing our preparation for the construction of the Tumas project,” Barnes said, adding that the company would only move to FID once uranium market conditions supported development.

Under the agreement, Tumas will be connected to the Namibian regional grid via a dedicated 22 km, 220 kV power line, with associated switching yard and substation infrastructure to be designed and built by Deep Yellow and handed over to NamPower after commissioning. Power supply will be supplemented by an on-site solar farm to be developed under a build, own, operate and transfer arrangement with an independent power producer.

The solar facility is designed to supply up to the full project power demand during daylight hours, accounting for at least 30% of total electricity requirements and reducing exposure to peak grid tariffs. Negotiations with a preferred solar supplier are continuing, while detailed design of the grid connection has commenced.

Progress is also being made on water supply arrangements. Fresh water for the project is planned to be sourced from the Swakopmund Reservoir, via a 65 km pipeline running parallel to the C28 highway. Draft water supply and development agreements have been received from NamWater, with negotiations now under way. Preliminary pipeline design has been completed and tenders for a design-and-construct contract received.

On the engineering front, Deep Yellow reported that detailed engineering for Tumas is now more than 60% complete, with the 3D engineering model exceeding 65%. More than 70% of major process plant equipment has been tendered and vendor data orders placed for all long-lead items. Project schedules, capital estimates and financial models are being updated in preparation for FID.

Early works at site are also advancing. Bulk earthworks, which began in October, are 24% complete and are expected to finish in March 2026. Temporary construction facilities, including access roads, water supply, offices and communications, have been established.

In parallel, project financing efforts continue to progress. The company said an independent technical expert had completed environmental and social due diligence for Nedbank, the mandated lead arranger, marking a key milestone towards securing project debt funding and enabling a move into the documentation phase.

Tumas is one of two advanced uranium projects underpinning Deep Yellow’s growth strategy, alongside Mulga Rock in Western Australia, as the company positions itself to become a diversified, mid-tier uranium producer.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Comments

Latest Multimedia

Photo of Martin Creamer
On-The-Air (12/12/2025)
12th December 2025 By: Martin Creamer

Showroom

MBE Minerals SA (Pty) Ltd
MBE Minerals SA (Pty) Ltd

Your global lifecycle technology & service partner for materials & minerals processing equipment for coal, iron ore, copper, manganese & other...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 10 December 2025
Magazine round up | 12 December 2025
12th December 2025

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.248 0.445s - 191pq - 2rq
Subscribe Now