Eskom boosts electricity supply in Mpumalanga
Eskom has installed and commissioned a new transformer at the Acornhoek substation in Bushbuckridge as part of its plans to upgrade electricity infrastructure and boost the power supply in Northern Mpumalanga.
The R144-million project started in September 2014 and consists of two phases‚ which includes the replacement of two old transformers with two new transformers that have bigger capacity to meet the growing electricity demand in areas such as Bushbuckridge‚ Acornhoek‚ Hoedspruit‚ Hazyview and other neighbouring towns like Phalaborwa.
The commissioning of this transformer forms part of Phase 1 of the transformation upgrade and will enable the substation to carry much more load‚ thus ensuring that the areas fed through this substation have a more reliable power supply‚ Eskom says.
The second phase of this transformational upgrade at Acornhoek is under way and involves civil works and the assembling of the second transformer. The second phase is expected to be completed by April 2016.
“Since 2005‚ Eskom has been expanding its generation and transmission capacity to meet the country’s growing demand for energy. Eskom’s nominal generating capacity in 2005 was 36 208 MW. The programme will increase this by 17 384 MW by 2021/22.
“The key generation expansion projects are the 4 764 MW Medupi and 4 800 MW Kusile coal-fired stations‚ and the Ingula pumped-storage scheme in the Drakensberg‚ which will deliver 1 332 MW of hydro-electricity during peak demand periods. Transmission line length and substation capacity will also increase substantially‚” the power provider says.
It adds that over the past 10 years‚ its new build programme has increased generating capacity by 6 137 MW‚ its transmission lines by 5 497 km and its transmission substation capacity by 27 565 MVA.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation