https://newsletter.en.creamermedia.com
Construction|Design|Financial|Materials Handling|Mining|OPENCAST|Platinum|PROJECT|Projects|Service|Surface|System|Underground|Infrastructure|Operations
Construction|Design|Financial|Materials Handling|Mining|OPENCAST|Platinum|PROJECT|Projects|Service|Surface|System|Underground|Infrastructure|Operations
construction|design|financial|materials-handling|mining|opencast|platinum|project|projects|service|surface|system|underground|infrastructure|operations

Growth outcomes inform approach to dividends ­as Northam digs in on RBPlat deal

Creamer Media picture.

Northam Platinum CEO Paul Dunne

Photo by Creamer Media

31st March 2022

By: Martin Creamer

Creamer Media Editor

     

Font size: - +

JOHANNESBURG (miningweekly.com) – Growth outcomes will inform Northam Platinum’s approach to dividends, the platinum group metals (PGMs) company stated in reporting 60%-higher half-year headline earnings a share.

Northam highlighted that it still had an option to acquire a further 3.29% in Royal Bafokeng Platinum (RBPlat), which would take its holding to within a hair’s breadth of 38%.

Northam CEO Paul Dunne described Northam’s investment in RBPlat as creating significant long-term optionality for Northam.

“It aligns perfectly with our growth, sustainability and diversification strategy, and the consequent introduction of Royal Bafokeng Holdings as a significant shareholder further strengthens our empowerment credentials,” said Dunne.

He added that the RBPlat investment was underpinned by underlying factors that included Northam’s view on the PGMs market, growth strategy, empowerment and community development.

The group’s share of earnings from RBPlat amounted to R128.4-million in the period. Furthermore, a dividend was declared subsequent to the period-end, of which the group’s share was R536.2-million.

In the six months to December 31, Northam production was largely unchanged at 351 359 four element (4E) ounces, when sales revenue grew 16.8% to R13.9-billion.

Earnings before interest, taxes, depreciation and amortisation increased by 19.1% to R6.4-billion.

Northam stated that its capital expenditure (capex) of R2.3-billion kept all projects on track, with the operating margin falling marginally to 42.2% on an increased profit margin of R5.9-billion.

Unit cash cost per equivalent refined platinum ounce increased by 18.6% to R32 814 per platinum ounce (H1 F2021: R27 660/Pt oz).

Dunne pointed to the dearth of mining investment for over a decade.

“There is a systemic global primary supply problem and it is the scarcity of new mining projects to replace the depleting profiles of currently operating, mature mines,” said Dunne.

“The eastern and western limbs of the Bushveld Complex host ore bodies with favourable platinum and rhodium loadings. These deposits are extremely rare and their intrinsic value will grow over time,” Dunne stated in a release to Mining Weekly.

In the period, Northam reported that it had made expansionary project progress at the Zondereinde Western extension and at Booysendal’s South mine.

It stated that the Eland mine was continuing to ramp up and the addition of the recently acquired Maroelabult section was adding considerable synergistic benefits.

Sustaining capital doubled to R776.9-million largely owing to the smelter furnace rebuild at Zondereinde and fleet replacements at Booysendal. Group capex for the full financial year is forecast to amount to R4.6-billion.

At Zondereinde mine, stoping is ramping up within the Western extension section, the deepening project has made further progress and reaming of number 3 shaft is on track. At the metallurgical facilities, upgrades to the materials handling infrastructure together with the planned rebuild of furnace 1 were completed. Capacity upgrades at the base metals removal plant have also begun, aligning with the group’s growth profile.

Booysendal South development is on track. Construction of surface infrastructure has been completed and underground development and upper group two (UG2) reef stoping ramp-up at the Central UG2 modules is progressing. Decline development at the South Merensky module is on track. Underground stoping has started at the BS4 UG2 module and will ramp up over the coming 12 months. The North aerial rope conveyor was commissioned in December 2021 and is operating within design parameters.

At Eland mine, development of the Kukama decline system has progressed well, as has strike development to connect with Maroelabult mine, where underground stoping ramp-up is in progress. In addition, opencast mining of UG2 commenced in the eastern portion of the mining right during the first quarter. First ore was delivered to the concentrator during the second quarter.

In a Stock Exchange News Service announcement, Northam described RBPlat’s metals mix as being complementary, with a higher relative platinum contribution, which, it said, fitted well within the broader Northam metals basket.

“The RBPlat assets are young, shallow and well capitalised and occupy a strategically important position in the western limb of the Bushveld Complex. Northam recognises the Royal Bafokeng Nation’s important contribution and ongoing legacy in respect of RBPlat and is cognisant of Northam’s responsibility in respect of the long-term sustainability of RBPlat’s operations and its impact on the broader communities and the Royal Bafokeng Nation as a whole,” said Dunne.

Edited by Creamer Media Reporter

Comments

 

Showroom

ESAB showroom image
ESAB South Africa

ESAB South Arica, the leading supplier of high-end welding and cutting products to the Southern African industrial market is based in...

VISIT SHOWROOM 
Environmental Assurance (Pty) Ltd.
Environmental Assurance (Pty) Ltd.

ENVASS is a customer and solutions-driven environmental consultancy with established divisions, serviced by highly qualified and experienced...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.256 0.346s - 173pq - 2rq
Subscribe Now