Heavy equipment demobilised after project completion
BIG DELIVERIES The components for the refinery project consisted of multiple shipments delivered to the purpose-built Dangote Quay Lekki in Lagos
ABNORMAL LOAD Mammoet transported a 2 000 t crude column, claimed to be the largest crude column globally
A MAMMOTH TASK Mammoet’s involvement concluded with the installation of a 1 240 t propylene mounded bullet
Heavy equipment lifting and transporting company Mammoet recently began demobilising equipment it had deployed at the Dangote Petroleum Refinery and Petrochemicals complex in Lekki Free Zone, in Nigeria.
The demobilising of the equipment began in July.
The equipment had been deployed there over the past two years, with Mammoet’s involvement concluding with the final 1240 t propylene mounded bullet installed.
Mammoet was contracted in 2018 to assist in the construction of the refinery, and said in a statement that the project had been delivered on time. The scope of Mammoet’s involvement consisted of the receiving, inland transport, on-site lifting and installation of hundreds of refinery components.
The $10-billion refinery, owned by Nigeria-based industrial multinational conglomerate Dangote Group, is designed to produce 650 000 bbl/d of refined petroleum products. It is expected to be Africa’s biggest petroleum refinery and the world’s biggest single-train facility.
Once onstream, the refinery will increase Nigeria’s oil exports and reduce its reliance on imports of petroleum products, thereby boosting economic growth in Nigeria, generating about 9 500 direct and 25 000 indirect jobs.
“We are very honoured that the Dangote Group entrusted us with the entire heavy lifting and transport scope for one of the most significant projects in Nigeria and the West Africa region,” said Mammoet CEO Paul van Gelder in a statement.
The components for the refinery project were sourced globally and consisted of multiple shipments delivered to the purpose-built Dangote Quay Lekki in Lagos. They were then transported to the project site.
Prior to installation, the components were stored temporarily on freshly paved Enviro-Mat, which is Mammoet’s proprietary solution for native soil improvement. The Enviro-Mat was deployed to provide the main crane hard stands. The refinery project is the largest commercial project to date to use the Enviro-Mat ground reinforcement solution.
“Enviro-Mat was the best solution for this job given the characteristics of the land, as well as the speed of application to such a large area,” said Mammoet heavy duty pavement director Ronald Kleinjan in a statement.
Combined with the native soil and cement, the Enviro-Mat additive increases the ground bearing capacity up to 50 t/m2. The Enviro-Mat is quicker to install than regular ground reinforcement solutions and therefore is advantageous on sites where ground reinforcement is required on a large area within a short timeframe.
“Enviro-Mat can be applied to any type of soil on site which means it is faster to install than conventional methods and requires less transport of materials and preparatory ground work, which also reduces carbon footprint,” Kleinjan added.
At the Dangote refinery, Mammoet applied the product to lay down areas, hard stands and crane pads equating to over 500 000 m2 of the site, which is located on reclaimed swamp land.
“As Mammoet’s presence in West Africa grows, it is a great flexible solution for projects in Africa because it is easy to transport to site, and it is quick and less disruptive to install,” Kleinjan said.
He noted that the African climate is ideal for applying the Enviro-Mat stabilisation technique.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation