Jindal, Zimbabwe in talks for $800m revamp of Hwange power plant
Zimbabwe’s State-owned power utility is in talks with Jindal Steel & Power over an $800-million upgrade of six units at its Hwange facility as it seeks to reduce blackouts.
The plant is the nation’s biggest, with an installed capacity of 1 500 MW and it frequently suffers breakdowns that cause nationwide power cuts.
The refurbishment will take place unit by unit over the next three to four years and almost double the station’s average output to 840 MW, Zesa chairperson Sydney Gata said in an internal circular seen by Bloomberg and verified by the company.
The Southern African nation faces an energy shortfall of as much as 540 MW during the high-demand winter period, which typically runs from June through August, and the utility often triggers rolling blackouts to balance supply and demand. The worst drought in four decades has compounded the crisis, cutting supplies from hydropower plants.
The revamp of units 1 to 6 at Hwange will ensure increased capacity, reliability, and extend their operational life by 15 to 20 years, Gata said.
Contractors are due to finish work on the fifth unit, which Zesa is paying for with internal funds, in April. It will arrange funding for the rest of the upgrade through a special-purpose vehicle, a company spokesperson said
The expansion of Hwange Units 7 and 8, commissioned by President Emmerson Mnangagwa last year, carries loan obligations that average $36-million a month as well as other undisclosed commitments to the African Export-Import Bank, according to the circular.
Jindal is also expected invest in an additional four new units at Hwange, which will add 1 200 MW of new capacity, Zesa said in the circular. Feasibility studies for the project have started, it said.
Zesa plans to install a 1 800 MWh battery-storage system to help meet electricity demand during morning and evening peaks, and has developed sites for solar-power generation of 400 MW, according to the circular.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation