Kathu plant's maintenance outage ensuring long-term efficiency in CSP operations
Power block at night. Lifting activities at the turbine hall ongoing to meet the tight schedule
Photo by Kathu Solar Park
Kathu Solar Park (KSP), one of South Africa's select few concentrated solar power (CSP) plants, located in the Northern Cape, recently underwent a 30-day offline period to complete its yearly maintenance.
Operational since 2019, KSP’s maintenance this year included a detailed inspection and refurbishment of its steam turbine – a core component that transforms thermal energy into electricity, making it essential to the plant’s functionality.
During the 30-day outage, the primary focus was a full inspection of the steam turbine, involving the dismantling of both high and low-pressure turbine cylinders.
This inspection included removing the last two stages of blades on the low-pressure turbine rotor for nondestructive testing of blade attachments.
Beyond the turbine, the team conducted substantial refurbishment on essential auxiliary systems, including turbine auxiliary systems, electrical maintenance and solar field maintenance that included the replacement of isolation valves to ensure reliable operation of the parabolic trough system.
Siemens Energy, the steam turbine’s original-equipment manufacturer, played a key role in the turbine inspection, bringing specialist skills to ensure the maintenance was completed with precision, says KSP.
Supplementing this expertise, 39 local workers were contracted for additional manpower, covering roles from unskilled to semi-skilled positions.
KSP says these local contractors supported the work scope while receiving rigorous training focused on safety, underscoring its commitment to both operational excellence and local community involvement.
“Unlike more modular solar PV systems, CSP plants like Kathu’s parabolic trough system have integrated components that must work in unison. This means that taking one part offline necessitates a full plant shutdown.
“The maintenance strategy aims to consolidate all necessary tasks into an annual outage, reducing overall downtime. This year’s 30-day outage differed from previous years, as it included major inspections and upgrades not previously required, such as opening the turbine casings and updating control systems for improved reliability,” says KSP technical manager Dr Gary de Klerk.
Among the upgrades completed, the turbine controller and balance-of-plant control system saw software enhancements designed to boost the reliability and efficiency of plant operations.
While these upgrades may not immediately reduce the plant’s environmental footprint, KSP says they contribute to a more reliable power generation system that supports the facility's long-term viability and performance.
The maintenance outage concluded on schedule, with critical tasks completed, including the turbine inspection, which found no issues in the last-stage rotating blade attachments.
Though some minor findings required attention, KSP says the maintenance team managed to address most within the allotted time. Any remaining tasks are scheduled for future maintenance, ensuring Kathu Solar Park continues to operate smoothly and efficiently.
“KSP’s 2024 maintenance reflects the rigorous standards required to sustain a CSP plant, with in-depth turbine inspections, system upgrades, and a comprehensive strategy that supports both operational reliability and local workforce involvement,” says KSP.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation