Kusile Unit 1 brought into full commercial operation well ahead of schedule

Eskom interim group CEO Johnny Dladla

Eskom interim group CEO Johnny Dladla

30th August 2017

By: Samantha Herbst

Creamer Media Deputy Editor

     

Font size: - +

Unit 1 of Eskom’s Kusile power station has been brought into full commercial operation, adding 800 MW of much-needed power to help stabilise the national power grid.

This means that construction and optimisation of the unit is complete and the operator, Eskom Generation, has taken over the plant and is running it on a regular basis.

The State power utility announced on Wednesday that the unit was completed well ahead of its scheduled commercial operation date of July 2018.

“This achievement shows that we have learnt lessons from the past and from other new-build projects, hence we managed to achieve this milestone ahead of revised schedule,” noted Eskom interim group CEO Johnny Dladla.

Dladla thanked the company’s employees, contractors and stakeholders for working together to ensure that the project remained on track.

“We value their commitment to the project whilst ensuring that we work safely to deliver on time and within budget,” he added.
 
Kusile power station is a greenfield coal-fired power plant located near the existing Kendal power station, near eMalahleni in Mpumalanga’s Nkangala district. The power station will comprise six units, each producing 800 MW for a total capacity of 4 800 MW. Upon completion in 2022, it will be the fourth-largest coal plant in the world.
 
Kusile is the first power plant in Africa to implement clean fuel technology such as flue-gas desulphurisation – a state-of-the-art technology used to remove oxides of sulphur, such as sulphur dioxide, from exhaust flue gases in power plants that burn coal or oil.

This technology is fitted as an atmospheric emission-abatement technology, in line with current international practice, to ensure compliance with air-quality standards, especially since the power station is located in a priority air shed area. 
 
The station has a total planned operational life of 50 years.

Edited by Creamer Media Reporter

Comments

Projects

Showroom

Hanna Instruments (Pty) Ltd
Hanna Instruments (Pty) Ltd

We supply customers with practical affordable solutions for their testing needs. Our products include benchtop, portable, in-line process control...

VISIT SHOWROOM 
Immersive Technologies
Immersive Technologies

Immersive Technologies is the world's largest, proven and tested supplier of simulator training solutions to the global resources industry.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 22 November 2024
Magazine round up | 22 November 2024
22nd November 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.084 0.178s - 206pq - 2rq
Subscribe Now