Lufeng nuclear power plant, China – update

Image of nuclear power plant

9th January 2026

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Lufeng nuclear power plant (NPP).

Location
Guangdong province, China.

Project Owner/s
Chinese State-owned energy China General Nuclear Power.

Project Description
The Lufeng NPP will comprise six nuclear reactors with a capacity of 1 000 MW each.

Units 5 and 6 will use Chinese-designed third-generation Hualong One reactors. The project is expected to generate about 52-billion kilowatt-hours of electricity a year, saving 15.77-million tons of standard coal and reducing carbon dioxide emissions by an estimated 42.69-million tons a year. The project will incorporate modular construction, digital building technologies and automated welding.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Construction of the Unit 5 and Unit 6 reactors started in 2022 and 2023 respectively, with construction scheduled to be completed in 2028 and 2029 respectively. Construction of Unit 1 started in February 2025.

Latest Developments
Shanghai Nuclear Engineering Research & Design Institute poured the first concrete for the nuclear island basemat of Lufeng Unit 2 on December 22, 2025.

Contractor China Nuclear Construction Corporation 22 (CNI22) has said that about 6 635 m3 of concrete was expected to be poured in a process lasting about 68 hours to form the foundation of Unit 2's nuclear island, measuring about 89 m long and 49 m at its widest point.

Key Contracts, Suppliers and Consultants
CNI22 (contractor).

Contact Details for Project Information
China General Nuclear Power, tel +86 755 84430888 or email IR@cgnpc.com.cn.
 

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

To advertise email advertising@creamermedia.co.za or click here

Comments

Latest Multimedia

Photo of Martin Creamer
On-The-Air (30/01/2026)
30th January 2026 By: Martin Creamer

Showroom

Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 
Lion Alcoblow ® - High speed breathalyser
Alco-Safe

Developed to exceed the latest EN 15964 standards for police breathalysers proving that it will remain accurate and reliable for many years to come.

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine cover image
Magazine round up | 30 January 2026
30th January 2026

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.131 0.296s - 189pq - 2rq
Subscribe Now