https://newsletter.en.creamermedia.com
Africa|Concrete|Construction|Consulting|Contractor|Design|Engineering|Housing|Installation|Pipelines|PROJECT|Projects|Proximity|Roads|Services|WSP|Equipment|Infrastructure
Africa|Concrete|Construction|Consulting|Contractor|Design|Engineering|Housing|Installation|Pipelines|PROJECT|Projects|Proximity|Roads|Services|WSP|Equipment|Infrastructure
africa|concrete|construction|consulting-company|contractor|design|engineering|housing|installation|pipelines|project|projects|proximity|roads|services|wsp|equipment|infrastructure

Microtunnelling used to build pipeline

An image of equipement being lowered for microtunnelin

DOING THE GROUNDWORK The Farm 694 project will be the longest and largest pipeline completed by mircotunneling in South Africa

18th March 2022

By: Nadine Ramdass

Creamer Media Writer

     

Font size: - +

The Farm 694 bulk civil engineering services project will, once completed, be the longest and largest diameter pipeline project constructed using microtunnelling in South Africa, says WSP Africa civil and municipal infrastructure civil engineer Darren Osborne.

Microtunnelling allowed for construction of the project – in Mitchell’s Plain, in the Western Cape – with minimum disruption.

The professional engineering and consulting teams were appointed by the Western Cape government’s Department of Human Settlements in September 2018 as a joint venture. WSP was appointed for the planning, detailed design and construction monitoring services while engineering consultancy firm MPAMOT was appointed for construction monitoring and contract administration services.

Construction commenced in August 2019 and the project is expected to be completed in August this year, with the majority of microtunnelling expected to be completed later this month.

Following the completion of microtunnelling, the existing pipelines will be connected to the newly constructed lines and, subsequently, to a wastewater treatment works collection chamber.

Owing to the project’s close proximity to existing services and roads, WSP decided to use the contractor’s alternative tender offer. The alternative tender proposed microtunnelling by the specialist subcontractor CSV as opposed to open-trench excavation to minimise disruptions to the project and surrounding community.

The project is part of the larger Kosovo Informal Settlement Upgrade Project, and assists in the developing and creating of housing opportunities for the Farm 694 project, as well the existing crossover settlement in the surrounding area. It will also be to the benefit of future development and upgrade of the region and alleviate capacity constraints within the greater Mitchell's Plain area and its catchment area.

The project entails the replacement of an existing degraded 2.4-km-long and up to 8-m-deep concrete sewer pipeline with a 1 200 mm- and 1 350 mm-diameter concrete sewer pipeline with a 3 mm high-density polyethylene (HDPE) lining. Construction includes all the associated structural manhole chambers, various live connections and installation of a new collection chamber at the Mitchell’s Plain Wastewater Treatment Works, explains Osborne.

A new sand trap structure along the sewer pipeline is also being constructed to remove grit and debris.

Meanwhile, WSP Africa civil technical director Du Toit Carstens says the project’s design and method of construction had to accommodate the existing services.

This process was prolonged by incomplete as-built information and unknown existing services, which, in turn, created delays in the project design and construction.

For example, an existing stormwater line was discovered, which had to be rerouted through microtunnelling to allow for the construction of the microchannel sewer line.

Carstens explains that, while most projects in Africa are done through open excavation, that method would be more difficult for the Farm 694 project, owing to its location in an existing built-up urban area and the length of the pipeline. Open excavation cost is of similar order of magnitude than microtunnelling, but more dangerous for construction workers and the surrounding communities, with various traffic and services disruptions.

By comparison, microtunnelling requires little open excavation, mostly for the manhole openings, which are used to lower the microtunneling equipment, making it safer.

The method also ensures that traffic, surrounding services and activities are less affected by the project or vice versa: “By doing microtunnelling, we’re going below schools terrains, intersections and other services structures that would be impacted on by open excavation,” explains Carstens.

However, the process does require that caution be exercised so that existing infrastructure above and below ground are not damaged, Carstens concludes.

Edited by Zandile Mavuso
Creamer Media Senior Deputy Editor: Features

Comments

 

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
John Ratcliffe
John Ratcliffe

At John Ratcliffe, we are aftermarket specialists for heavy-duty on and off-road vehicles. We engineer and retrofit advanced safety systems, engine...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Magazine round up | 13 December 2024
Magazine round up | 13 December 2024
13th December 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.22 0.312s - 187pq - 2rq
Subscribe Now