https://newsletter.en.creamermedia.com
Africa|Business|Construction|Cutting|Environment|Infrastructure|PROJECT|Project Management|Projects|Risk Management|Sanitation|Service|Underground|Water|Infrastructure
Africa|Business|Construction|Cutting|Environment|Infrastructure|PROJECT|Project Management|Projects|Risk Management|Sanitation|Service|Underground|Water|Infrastructure
africa|business|construction|cutting|environment|infrastructure|project|project-management|projects|risk-management|sanitation|service|underground|water|infrastructure

Opinion: Why so many public infrastructure projects go over time and budget

Dr Sean Phillips

Dr Sean Phillips

29th January 2026

     

Font size: - +

This opinion article, written by Department of Water and Sanitation director-general Dr Sean Phillips in his personal capacity, outlines the many causes for public projects being delayed or running over budget. Phillips argues that this is not only the result of poor planning and execution and suggests that there is a need for society to gain a better understanding of the nature of construction projects.

I typed the question “What percentage of large construction projects globally go over time and over budget?” into Google AI. It searched all the available relevant research papers and reports on the internet and gave me the following answer: “A vast majority of large construction projects globally go over time and budget, with studies showing 90% experiencing cost overruns or delays, often significantly, with average cost overruns of 28% to 79% and delays of 50% or more, highlighting that finishing on time and budget is extremely rare.”

Clearly, the problem of public infrastructure projects going over time and budget is not unique to South Africa. The causes all over the world lie in the nature of the construction process. A large construction project is a process involving many interrelated construction activities implemented by different specialist contractors, suppliers and service providers. Scheduling and co-ordination of these activities can be extraordinarily complex, and a delay in one activity can have a knock-on effect on others.

There are many unforeseeable and unpredictable risks in construction, including unusually heavy rain, labour strikes, community disruption, undetected underground rock and nonperformance by subcontractors or suppliers, to name a few. Some of these risks can be mitigated through risk management measures. For example, the risk of community disruption can be mitigated — but not ruled out altogether — by engagement and consultation with the community from the initial stages of the project. Other risks, such as the weather, are uncontrollable.

When project managers and engineers say how long a project is going to take and how much it will cost, they have to make assumptions about the risks, and their time and cost projections can only ever be estimates. Even with the best possible planning and project management, the risks can result in projects going over the estimated time and budget.

“Scope creep” — when decisions are made to change the scope of a project after the implementation contracts have been awarded — is also a frequent cause of time and cost overruns. Decision-makers often do not appreciate the impact of such changes in scope on the time frame and cost of the project.

Even with the best possible planning and project management, the risks can result in projects going over the estimated time and budget. In addition, sometimes projected costs are in constant prices, and do not include the effect of inflation, which can result in considerable increases in actual final project costs.

Project managers and planners are often put under intense pressure to set ambitious and optimistic, as opposed to realistic, timeframes and budgets. Projects often need to be implemented as quickly as possible to meet urgent social or economic needs.

In addition, decisions to proceed with projects are sometimes made late, and the project’s managers are then expected to make up for lost time through accelerated project implementation processes.

Overruns amid uncontrollable risks

However, pressure to accelerate implementation can have the unintended consequence of actually increasing the likelihood of projects going over time and over budget. For example, intense pressure to reduce timeframes can result in project managers cutting corners and not doing things properly, which in turn can result in things needing to be redone or in quality problems, adding to timeframes and costs.

Broader society can add to this pressure, including the media, civil society and political leaders. Community leaders sometimes make statements like: “They told us the project would be finished by now, but it’s not. Now they have a new completion date — they keep lying to us about when the project is going to be completed.” These sentiments are often amplified in the media.

The media and others can also sensationalise the fact that a project is over time or over budget, with dramatic headlines that a project is a year past its planned completion date, or 25% over budget, and calls for heads to roll. However, in the context of the answer provided by Google AI above, if a four-year project is completed a year late or is 25% over budget, the project has actually performed well by international standards.

Construction mafia

When projects go over time or budget, auditors often make findings of poor performance and “weaknesses in project management”, even if the delays are caused by uncontrollable risks.

Due to the prevalence of the “construction mafia” in South Africa, and its associated culture of violence and intimidation, project managers put their lives at risk when they conduct site visits or attend site meetings. In one instance, several project managers of the department of water & sanitation were forcefully detained by disgruntled subcontractors.

In another instance, a member of a delegation of a local “business forum” attended a site meeting armed with an automatic weapon. Some of our project managers have asked the department to provide them with guns so that they can defend themselves when they go to site.

All this pressure adds to the stress of overloaded project managers and can make them ill, demoralised or demotivated. It is difficult to attract and retain good project managers to work in this environment. Managing complex construction projects is an incredibly stressful job on its own, even without these kinds of social and political pressure.

None of the above provides any excuses for poor planning, poor infrastructure procurement, poor contract management or poor project management. Where projects have been poorly managed, there must be accountability. Rather, it indicates that there is a need for society in general to have a better understanding of the nature of construction projects, and to understand time and cost overruns in this context.

This article was originally appeared in Business Day.

Edited by Creamer Media Reporter

Article Enquiry

Email Article

Save Article

Feedback

To advertise email advertising@creamermedia.co.za or click here

Comments

Showroom

The Beneficiation Academy
The Beneficiation Academy

The Beneficiation Academy is a certified training institution that follows all compliance legislation and is accredited with various Sector...

VISIT SHOWROOM 
ABB Electrification
ABB Electrification

Electrifying the world in a safe, smart, and sustainable way, ABB Electrification is a global technology leader in electrical distribution and...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







301

sq:0.144 0.242s - 180pq - 2rq
Subscribe Now