Port of Ngqura liquefied natural gas import terminal, South Africa

LNG tanks

29th November 2024

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Port of Ngqura liquefied natural gas (LNG) import terminal.

Location
Eastern Cape, South Africa.

Project Owner/s
Transnet National Ports Authority (TNPA) and Industrial Development Corporation (IDC).

Project Description
TNPA is proposing to build an LNG import terminal that will provide natural gas importation infrastructure bulk services.

Two options have been proposed.

The first option proposes a floating storage and regasification unit (FSRU) with a design life of 50 years, marine infrastructure (a berth), bulk services and associated gas distribution pipelines within the port 
boundary.

The LNG breakwater berth will have the capability to expand to 2.8-million tons a year of LNG. It will accommodate a liquefied natural gas carrier (LNGC) with a capacity of 125 000 m3 to future demand at 267 000 m3. 

The FSRU will have a capacity of 170 000 m3 and a deadweight of 95 000 t.

Option 2 proposes a land-based storage and regasification unit with a design life of 50 years. 

The same marine infrastructure used for Option 1 remains, while a new 2.5-km-long cryogenic pipeline is developed to transfer LNG from the berth (at breakwater) to the new land-based storage and regasification terminal adjacent to the port boundary.

This option is planned to deliver 500 000 t/y to 2.8-million tons a year of LNG.

The design of LNG breakwater berth will accommodate an LNGC with a capacity of 125 000 m3 to 267 000 m3. The LNGC will have a deadweight of 95 000 t and even higher.

Potential Job Creation
Not stated.

Capital Expenditure
Not stated.

Planned Start/End Date
Not yet determined.

Latest Developments
A request for proposals was issued in September 2024. The bid closed on October 3, 2024.

Key Contracts, Suppliers and Consultants
No details available.

Contact Details for Project Information
TNPA, email tnpamediadesk@transnet.net.
IDC, tel +27 11 269 3000 or email media@idc.co.za.

Edited by Martin Zhuwakinyu
Creamer Media Senior Deputy Editor

Comments

Latest News

Magazine cover image
Coal ash liability can be asset for multiple industries
Updated 2 hours 36 minutes ago By: Marleny Arnoldi

Showroom

Klüber Lubrication
Klüber Lubrication

Klüber Lubrication ensures that the world’s essential systems—drive units, machines, and water flow—operate efficiently, sustainably, and reliably...

VISIT SHOWROOM 
Weir
Weir

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.274 0.376s - 192pq - 2rq
Subscribe Now