Ramokgopa ‘worried and extremely upset’ over Koeberg outage slips
Electricity Minister Dr Kgosientsho Ramokgopa says he is “worried and also extremely upset” about developments at the Koeberg nuclear power station, where fears have increased that both units could be out simultaneously later this year owing to another Unit 1 outage slip.
Speaking during his weekly Energy Action Plan briefing, Ramokgopa said “he was none the wiser” about the status of the current Unit 1 outage, despite having met with Koeberg managers during the week.
He said he would be requesting the Eskom board to provide him with a full report regarding the status of the Unit 1 outage, which began on December 10 and was initially scheduled to continue for about 180 days and return to service in June.
The outage includes the replacement of the unit’s three steam generators; one of several prerequisites for securing a new licence to operate the unit for a further 20 years beyond its current July 2024 shutdown date.
Eskom is also seeking to secure a separation of Unit 2’s licence to reflect the fact that it entered into commercial operation more than a year after Unit 1 and should, thus, be allowed to continue to operate beyond July next year.
In March, Eskom confirmed that the initial Unit 1 return-to-service date was no longer achievable but indicated that it would be reintroduced before Unit 2 was shut in September for a similar outage.
It has since emerged that the schedule might well have slipped again and that Unit 1 may now be returned only in October, by when the Unit 2 outage could be under way leaving the loadshedding-prone South African grid without more than 1 800 MW of generation.
Ramokgopa did not respond to a question regarding whether a forensic investigation would be launched into the delays and possible financial irregularities at Koeberg, saying that the launching of such a probe would be the prerogative of the board.
“Where there are significant failures in delivering a project of this magnitude valid and genuine questions will be asked and they must be responded to.
“If they get to be responded to through a forensic investigation, so be it,” Ramokgopa said.
He added that he had already formulated a personal view of the issues confronting Koeberg, but that he was not in a position “to ventilate them in public”.
“But I do say that is the basis of me saying I'm worried and also extremely upset about what is unfolding at Koeberg.”
The Minister also did not comment on the cost of the project to extend the life of Koeberg.
The cost was initially pegged at R20-billion, but it has been confirmed that the actual cost will be far higher.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation