Ummbila Emoyeni wind energy facility, South Africa – update


Name of the Project
Ummbila Emoyeni wind energy facility.
Location
Mpumalanga, South Africa.
Project Owner/s
Coal producer Seriti Resources and its renewable-energy subsidiary Seriti Green.
Project Description
Ummbila Emoyeni has been designated as a Strategic Integrated Project by the Department of Public Works and Infrastructure. The wind farm will be the first renewable-energy project to be developed in Mpumalanga.
The wind farm project forms part of the coal miner’s strategy of diversifying its offering to more than coal, in a sustainable way, for it to play its role in the country’s just energy transition journey.
The initial 155 MW phase is the first of eight for the planned 900 MW renewable-energy cluster, which comprises 750 MW of wind energy facilities and 150 MW of solar PV plants.
Once built, the wind farm will result in more than 75% of the energy consumption from Seriti’s existing operations switching from coal to renewable energy, helping to mitigate its Scope 1 and 2 greenhouse-gas emissions.
The overall project will also include 800 MWh of storage capacity.
Potential Job Creation
The construction of the project is expected to create about 800 jobs.
Capital Expenditure
The energy cluster will involve R25-billion investment.
Seriti Resources has partnered with Standard Bank, Rand Merchant Bank and Venn Energy in the financing and development of the 155 MW project, which is estimated at R4.5-billion.
Planned Start/End Date
Construction of the first phase has started with completion expected in the second quarter of 2026.
Latest Developments
Seriti Green has reported that all financing conditions for the Ummbila Emoyeni facility have been met and financing is in place to start construction.
This initial phase power will be generated by Seriti Green and wheeled through the national grid to Seriti Resources’ coal mining operations, consequently reducing its carbon emissions by 5.1-million tonnes a year.
Key Contracts, Suppliers and Consultants
Vanguard (transport).
Contact Details for Project Information
Seriti, tel +27 11 047 7000 or email info@seritiza.com.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation