Ramokgopa deeply worried about prospect of both Koeberg units being unavailable due to Unit 1 outage slip
Electricity Minister Dr Kgosientsho Ramokgopa has expressed deep concern that another delay to the return to service of Koeberg Unit 1 could result in both of the nuclear power station’s units being out of service simultaneously later this year.
The unit is currently undergoing a long-duration outage that includes the replacement of its three steam generators, which is one of the preconditions for extending the plant’s life for 20 years.
Speaking during his weekly update on the implementation of the Energy Action Plan, which followed a recent period of intense Stage 6 loadshedding, the Minister revealed that he was growing increasingly concerned that there could be an outage “overlap”, which would result in a period where there would be no production from Koeberg.
“That would represent a net loss of 920 MW from where we are currently [with Unit 1 being out of service]. That’s a huge dent on our generating capacity.”
Ramokgopa indicated he had planned to meet with the leadership of Koeberg last week for a report on the outage, but he had been unable to do so and that the meeting would take place this week instead.
“I've asked for a more detailed report, and the more we get an indication of what the issues are, the more we are getting very, very, very worried. It is something that requires urgent attention.”
The Unit 1 outage began on December 10 and was initially scheduled to continue for about 180 days and returned to service in June.
In March, however, the State-owned utility confirmed that the early June return to service date was “no longer achievable”, but that it would be reintroduced before Unit 2 was shut in September for a similar outage. This, after a previous attempt to replace the Unit 2 steam generators was postponed when it emerged that Eskom’s storage facilities had not been completed in time.
It is understood that Unit 1 may now only be returned in October, but this has not yet been confirmed by Eskom despite several Engineering News enquiries in recent days.
Eskom indicated to Engineering News last week that it was planning to issue a formal statement on developments at Koeberg, but no statement had yet been released by the time Ramokgopa held his briefing.
Eskom did confirm, however, that all three Unit 1 steam generators had been successfully replaced and welding in these generators had commenced.
“We would also like to assure the public that it is our commitment to ensure that we prioritise safe working standards on this project,” the utility added in a written response to questions posed.
No answers were provided regarding the effect of the outage slips on Eskom’s efforts to secure a Long-Term Operation (LTO) licence.
Unit 1’s 40-year licence expires on July 21, 2024, and it is currently uncertain whether Eskom has received confirmation of a separate licence validity date for Unit 2, to reflect the fact that the unit came into operation a year-and-a-half after Unit 1 in November 1985.
Securing the licence change request for Unit 2 has been identified as a key priority and risk for the operation of Koeberg for a further 20 years.
Comments
Research Reports
Projects
Latest News
Showroom
Since 1919, Victaulic’s innovative solutions and design services continue to increase construction productivity and reduce risk, ensuring projects...
VISIT SHOWROOMThe SAIMM started as a learned society in 1894 after the invention of the cyanide process that saved the South African gold mining industry of the...
VISIT SHOWROOMPress Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation