https://newsletter.en.creamermedia.com
Business|Coal|Energy|Eskom|Financial|Gas|Generators|Nuclear|Power|Safety|Service|Turbines|Maintenance|Turbines
Business|Coal|Energy|Eskom|Financial|Gas|Generators|Nuclear|Power|Safety|Service|Turbines|Maintenance|Turbines
business|coal|energy|eskom|financial|gas|generators|nuclear|power|safety|service|turbines-company|maintenance|turbines-person

With R9.2bn spent since April, govt insists Eskom is not exceeding diesel budget

The Atlantis OCGT plant

The Atlantis OCGT plant

13th August 2023

By: Terence Creamer

Creamer Media Editor

     

Font size: - +

Government reports that Eskom has spent R9.2-billion on diesel since the start of the State-owned utility’s financial year on April 1, which it claims to be marginally below an initial budget for the period of R9.7-billion.

The Presidency’s Rudi Dicks provided the figure during a regular weekly update on the implementation of the Energy Action Plan, during which Electricity Minister Dr Kgosientsho Ramokgopa reiterated that it had always been Eskom’s intention to use the open-cycle gas turbines to reduce winter loadshedding.

The move to clarify Eskom’s diesel spend came amid ongoing concern that the R30-billion reportedly set aside for diesel for the 2023/24 financial year was both exorbitant and insufficient in light of the ongoing underperformance of the coal fleet, and a four-month-plus outage slip at Koeberg Unit 1.

Dicks initially reported that R12.4-billion had been spent on diesel up until the end of July, but later clarified that the figure included electricity purchases from private open-cycle gas turbines and that Eskom’s own year-to-date diesel spend had been R9.2-billion.

Ramokgopa used the presentation to provide greater detail on the performance of individual coal stations, as well as to express his hope that Koeberg Unit 1 would be returned to service on November 3 and ahead of the Unit 2 outage, which is scheduled to begin on November 7.

The Minister provided a breakdown of three clusters of coal stations, with the first cluster (comprising Medupi, Lethabo, Camden, Duvha and Majuba) said to be operating at an energy availability factor (EAF) that was consistently better than 60%.

The EAF of the second cluster – comprising Matla, Arnot, Kendal and Kriel – was lower at between 40% and 59%, and had become a major area of focus for Eskom, as well as private specialists recruited with the support of the R100-million business-financed Resource Mobilisation Fund.

Particular attention was being given to interventions aimed at enabling power stations such as Kendal and Kriel to ramp up production without breaching air pollution thresholds.

There were also safety, cost and emission assessments under way as part of a controversial bid to finalise the delayed decommissioning of Camden in light of its relatively strong performance.

The Koeberg nuclear station has also been included in the second cluster, given its current EAF of only 48%, precipitated largely by a protracted Unit 1 outage, which began in December and was initially scheduled to be completed in June.

Eskom generation head Bheki Nxumalo said the primary goal was to ensure that Unit 1 was brought back into operation by November 3 or sooner, with any “consequence management” arising from the delays to follow only once the unit had been returned.

He reported that the major works relating to the replacement of the unit’s three steam generators (a requirement for a plan by Eskom to extend Koeberg’s life by a further 20 years from July next year) had been completed and that the current focus was on the “normal” maintenance works that Eskom had experience in conducting.

The third cluster included Hendrina, Grootvlei, Kusile and Tutuka, where the EAF remained well below 40%, with Tutuka having operated at an EAF of only 13% in July and with only one Kusile unit currently in operation, following the flue duct collapse of October last year.

Ramokgopa said the aim remained to recover 6 000 MW of capacity from the coal fleet relative to the lows of May and reported that about 2 000 MW of that capacity had already been recovered.

Edited by Creamer Media Reporter

Comments

Showroom

SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)
SAIMC (Society for Automation, Instrumentation, Mechatronics and Control)

Education: Consulting with member companies to obtain the optimal benefits from their B-BBEE spending, skills resources as well as B-BBEE points

VISIT SHOWROOM 
Weir
Weir

Weir Minerals Europe, Middle East and Africa is a global supplier of excellent minerals solutions, including pumps, valves, hydrocyclones,...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

Photo of Martin Creamer
On-The-Air (15/11/2024)
15th November 2024 By: Martin Creamer

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.251 0.355s - 221pq - 2rq
Subscribe Now